Cost with human resources

As the project is executed within the academic environment, the basis for calculating the menber / hour was based on the 2016 Management Report, which details the annual cost per student of R$ 26,040.00. To carry out the calculation it was still considered that the course time is 5 years, with a total of 240 credits and that each credit is equivalent to 15 hours.

Average cost of the member / hour =
(Annual cost x course time) ÷ (course credits x hours / credit) =
(R$ 26,040.00 x 5 years) ÷ (240 credits x 15 hours / credit) = R $ 36.16/h

In order to obtain the total value per member of the Design and Techniques of Programming (11 people) it was considered that each work on average 5 hours/week and that the project has a duration of 15 weeks.

Average cost per member =
Average cost of the member/hour x hours worked/week x total of weeks =
R$ 15,30 * 5 hours/week * 15 weeks = R$ 2712,50.

Below you can see a table with the data mentioned:

Human Resource Cost
Annual Student Cost R $ 26,040.00
Course Time 5
Course Credits 240
Hours/Credit 15
Hours/week 5
Weeks of work 15
Total per member R$ 2,712.50
Total Team R$ 22,958,33

Cost of acquisitions: services and equipment.

Each team member has their own notebook for the exclusive use of it. As each member already owns a notebook of their choice and customized, a market research was conducted in search of a notebook with medium configurations, to be considered as basis for calculating, the model chosen was a Dell Inspiron 14 5000 in value of R$ 1,749.00.

The costs related to services were considered the fixed Internet of the Vivo operator with a speed of 25 mb/s in the amount of R$ 115.00.

Description Unit of measurement About Us Unit Cost (R $) Subtotal
* Equipment *
Computers / Notebook Unit 11 R$ 1,749.00 R$ 19,239.00
* Services *
Internet 25 Mbps (Live) Month 5 R$ 115,00 R$ 575,00

Total cost

The final cost of the project was defined according to the sum of the cost of human resources, equipment and services. Totaling 49,651.50.

Description Unit of measurement Quantity Unit Cost (R$) Subtotal
Computers / Notebook Unit 11 R$ 1,749.00 R$ 19,239.00
Internet 25 Mbps (Live) Month 5 R$ 115.00 R$ 575.00
Team Members People 11 R$ 2,712.50 R$ 29,837.50
Total Purchases R$ 49,651.50